Work at the valley station of the 3-S Pardatschgrat in October
- testing operation
- work at the facade (glass, aluminium, steel)
- concrete work for the counter bearing ski-bridge Prenner
- interior construction (joiner, floorer, tiler, painter...)
- expansion sportshop and skidepot
- initial operation gas heating